Biometano Candasnos is a biomethane and biofertiliser production project located in the municipality of Candasnos (Huesca). The project will valorise 184,500 tonnes per year of livestock manure and vegetal waste to obtain biomethane, biofertiliser and biogenic CO2. 

Plant Diet

185 kt of agricultural and

livestock waste

Biomethane Production

110 GWh/yr of biomethane

injection

Local
Employment

+40 direct & indirect jobs created

Project Investment

+25M€ of project investment

Permitting process of Candasnos project

October 2024

December 2024

May 2025

March 2026

INAGA

AAI & EIA Application

​

Autorización Ambiental Integrada & Evaluación de Impacto Ambiental constitute the principal administrative procedures for the authorization of the project.

Government of Aragón

​Regional Interest Declaration

​​

The Regional Interest Declaration (DIIA in Aragón), granted on December 2024, demonstrates institutional support and reduces administrative processing timelines by half.

INAGA

Public Information Period

​

The public information period for the project started in May 2025.

INAGA

​AAI date

​

Autorización Ambiental Integrada resolution expected by March 2026.